Foreman 1.11 Schedule

To be timed for approximately three months after the 1.10.0 release.

Dates are subject to change and may slip.

  1. approx 7th October 2015: development start (1.10-stable branched)
  2. Weds 23rd December: 1.10.0 released, 1.11.0 due three months later
  3. Mon 4th January 2016: branch warning to -dev
  4. Weds 17th - Fri 19th Feb: branch to 1.11-stable
  5. Thurs 25th Feb: 1.11.0-RC1, blocked by:
    • apipie-rails build issue, #13710
    • kafo/Ruby 1.8.7 issue, #13802
    • i18n/apipie build issue, #13804
    • jwt compatibility issue, #13866
  6. Fri 11th Mar: 1.11.0-RC2, blocked by:
    • rubocop/rake issue, #14114
    • select2-rails issue, #14045
    • STI/reports authz issue, #13545 should get in too
  7. Wed 16th Mar: release Hammer CLI 0.6.1 to 1.11 repos
  8. Wed 23rd Mar: 1.11.0-RC3, to include:
    • compute attribute and NIC handling fixes (#14179, #13980)
    • Hammer CLI NIC attribute fix (#14267)
  9. Fri 1st Apr: release 1.11.0
  10. Weds 20th April: release 1.11.1
  11. Thurs 19th May: release 1.11.2
  12. Tues 21st June: release 1.11.3
  13. Mon 25th July: release 1.11.4
    • to include #15268 for CVE-2016-4475
  14. no further updates planned