Foreman 1.24 Schedule

Release manager: Tomer Brisker
Release engineer: Zach Huntington Meath
To be timed for approximately three months after the 1.23.0 release (see Foreman_123_Schedule).

Dates are subject to change and may slip.

  1. 30 July: development start (1.23-stable branched)
  2. 30 September: 1 month branch warning to developers
  3. 21 October: stabilization period
  4. 28 October: branch to 1.24-stable
  5. approx every two weeks since then, new release candidate until stable (usually 2 or 3 needed)
  6. approx early December: release 1.24.0