Foreman 1.12 Schedule

To be timed for approximately three months after the 1.11.0 release (see Foreman_111_Schedule).

Dates are subject to change and may slip.

  1. Weds 17th Feb: development start (1.11-stable branched)
  2. Fri 1st Apr: 1.11.0 released, 1.12.0 should be three months later
  3. Weds 20th April: branch warning to -dev
  4. Tues 31st May: branch to 1.12-stable
  5. Mon 6th June: RC1
  6. Tues 21st June: RC2
  7. Mon 4th July: RC3
  8. Mon 11th July: release 1.12.0
  9. Mon 25th July: release 1.12.1
  10. Weds 24th August: release 1.12.2
  11. Tues 20th September: release 1.12.3
    • fixes compatibility with Puppet Server 2.6.0
  12. Fri 21st October: release 1.12.4
  13. no further releases planned