Foreman 1.13 Schedule

Release manager: Dominic Cleal

To be timed for approximately three months after the 1.12.0 release (see Foreman_112_Schedule).

Dates are subject to change and may slip.

  1. Tues 31st May: development start (1.12-stable branched)
  2. Mon 11th July: 1.12.0 released, 1.13.0 should be three months later
  3. Tues 9th August branch warning to -dev
  4. Mon 5th - Weds 7th September: branch to 1.13-stable
  5. Tues 13th September: release 1.13.0-RC1
  6. Tues 27th September: release 1.13.0-RC2
  7. Thurs 6th October: release 1.13.0
  8. Weds 26th October: release 1.13.1
  9. Sat 26th November: release 1.13.2
  10. Wed 21st December: release 1.13.3
  11. Thurs 26th January: release 1.13.4
  12. no further releases planned

Useful links