Foreman 1.8 Schedule

Normal quarterly release: 1.7.0 was start of December, so aiming for start of March, or start of April, given the Christmas period.

Dates are subject to change and may slip.

  1. Tue 28th October: development start (1.7-stable branched)
  2. Mon 9th February: branching warning to -dev
  3. Tue 24th February: branch to 1.8-stable
  4. Wed 11th March: 1.8.0-RC1
    • delayed due to networking/CR fixes in #9480 and major installer module releases
  5. Thu 26th March: 1.8.0-RC2
  6. Mon 13th April: 1.8.0-RC3
    • adding as a few blockers remain
    • delayed due to work surrounding #9947 CVE
  7. Tue 28th April: tag and release 1.8.0
    • delayed due to #10111 and #10186
  8. Wed 20th May: tag and release 1.8.1
  9. Tue 16th June: tag and release 1.8.2
  10. Wed 19th August: tag and release 1.8.3
  11. Tue 15th September: tag and release 1.8.4

No further releases planned.