Capsule sync UI inaccurately reports progress due to two tasks (sync and publish)

Added by Brad Buckingham over 1 year ago. Updated about 1 month ago.

Status:
New
Priority:
Normal
Assignee:
-
Category:
Foreman Proxy Content
Target version:
Difficulty:
Triaged:
Yes
Bugzilla link:
Pull request:
Team Backlog:
Brad
Fixed in Releases:
Found in Releases:

Description

Cloned from https://bugzilla.redhat.com/show_bug.cgi?id=1419196

Description of problem:

When a capsule is being synced, the sync and publish tasks are reported as a single task. The progress for a finished sync task is not reported until the publish task is also finished. When a lot of repositories are being synced onto a capsule at one time, the publish tasks don't start running until a lot of the sync tasks finish. As a result it looks like no progress is made for a long time.

History

#1 Updated by Brad Buckingham over 1 year ago

  • Subject changed from Capsule sync UI inaccurately reports progress to Capsule sync UI inaccurately reports progress
  • Target version set to 163

#2 Updated by Justin Sherrill over 1 year ago

  • Legacy Backlogs Release (now unused) set to 211

#3 Updated by Brad Buckingham over 1 year ago

  • Target version changed from 163 to 169

#4 Updated by Justin Sherrill over 1 year ago

  • Subject changed from Capsule sync UI inaccurately reports progress to Capsule sync UI inaccurately reports progress due to two tasks (sync and publish)

#5 Updated by Justin Sherrill over 1 year ago

  • Legacy Backlogs Release (now unused) changed from 211 to 228

#6 Updated by Brad Buckingham over 1 year ago

  • Target version changed from 169 to 178

#7 Updated by Brad Buckingham over 1 year ago

  • Target version changed from 178 to 160

#8 Updated by Brad Buckingham over 1 year ago

  • Priority changed from High to Normal
  • Legacy Backlogs Release (now unused) changed from 228 to 114