Actions
Bug #18824
closedPerformace issues on creating on host on a vmware compute resource with many many networks
Status:
Duplicate
Priority:
Normal
Assignee:
-
Category:
Compute resources - VMware
Target version:
-
Description
Hi,
we have da datacenter size vmware farm. We approx 4000 network on 2 dvs on our farm.
Currently, we evaluate foreman connection to our vmware cluster. After click on "New Host", select deploy on vmware (compute resource), foreman need some minutes to load all the data from the backend. After submit the form, the foreman needs again some minute to create the virtual machine.
It's terrible slow.
Actions