Actions
Bug #25655
closedSync plans does not start 'repositories sync' first time as per defined "Start Date" and same happened for all 'hourly/daily/weekly' Intervals
Status:
Closed
Priority:
Normal
Assignee:
Category:
-
Target version:
Difficulty:
Triaged:
No
Bugzilla link:
Pull request:
Description
Cloned from https://bugzilla.redhat.com/show_bug.cgi?id=1655595
Description of problem:
Sync plans does not start 'repositories sync' first time as per defined "Start Date" and same happened for all 'hourly/daily/weekly' intervals
Version-Release number of selected component (if applicable):
Satellite 6.5.0 snap 6
How reproducible:
Always
Steps to Reproduce:
1. Go to Satellite GUI:
Content => Sync Plans => Create Sync Plan => set internal 'hourly/daily/weekly' => Submit
Click on same sync plan => Products => select and add product
2. Keep check the product repository sync as per first sync("Start Date")
Actual results:
No sync task will create as per defined "Start Date" .
Expected results:
Added product repositories should start syncing as per "Start Date".
Additional info:
Updated by Samir Jha about 6 years ago
- Project changed from Katello to foreman-tasks
- Category deleted (
Sync Plans) - Assignee set to Samir Jha
Updated by The Foreman Bot about 6 years ago
- Status changed from New to Ready For Testing
- Pull request https://github.com/theforeman/foreman-tasks/pull/380 added
Updated by Anonymous about 6 years ago
- Status changed from Ready For Testing to Closed
Applied in changeset 46933a33e74c2c66c7621964ecda9c9ced977885.
Updated by Ivan Necas almost 6 years ago
- Target version set to foreman-tasks-0.14.5 (Foreman 1.20)
- Fixed in Releases foreman-tasks-0.14.5 (Foreman 1.20) added
Actions