closed

Change configuration steps log message frequency and wording

Added by William Clark about 3 years ago. Updated about 3 years ago.

Status:
Closed
Priority:
High
Assignee:
Fixed in Releases:
Found in Releases:

Description

Cloned from https://bugzilla.redhat.com/show_bug.cgi?id=1929694

Description of problem:
Here is the output of Satellite-installer command on Satellite 6.9 system, we can notice that the new line is printed in multiple of 100. It makes this part of the output look very long and it is not very much helpful from the customer's point of view.

Instead of this output we should show the progress report of Configure tasks in a single line with a progress bar or % of completion.

2021-02-17 18:28:39 [NOTICE] [configure] Starting system configuration.
The total number of configuration tasks may increase during the run.
Observe logs or specify --verbose-log-level to see individual configuration tasks.
2021-02-17 18:28:56 [NOTICE] [configure] 100 out of 2315 done.
2021-02-17 18:28:56 [NOTICE] [configure] 200 out of 2315 done.
2021-02-17 18:28:56 [NOTICE] [configure] 300 out of 2315 done.
2021-02-17 18:29:29 [NOTICE] [configure] 400 out of 2315 done.
2021-02-17 18:29:30 [NOTICE] [configure] 500 out of 2315 done.
2021-02-17 18:29:32 [NOTICE] [configure] 600 out of 2315 done.
2021-02-17 18:29:32 [NOTICE] [configure] 700 out of 2317 done.
2021-02-17 18:29:32 [NOTICE] [configure] 800 out of 2317 done.
2021-02-17 18:29:33 [NOTICE] [configure] 900 out of 2319 done.
2021-02-17 18:29:35 [NOTICE] [configure] 1000 out of 2320 done.
2021-02-17 18:29:35 [NOTICE] [configure] 1100 out of 2321 done.
2021-02-17 18:29:35 [NOTICE] [configure] 1200 out of 2323 done.
2021-02-17 18:29:36 [NOTICE] [configure] 1300 out of 2325 done.
2021-02-17 18:29:36 [NOTICE] [configure] 1400 out of 2327 done.
2021-02-17 18:29:44 [NOTICE] [configure] 1500 out of 2327 done.
2021-02-17 18:29:44 [NOTICE] [configure] 1600 out of 2329 done.
2021-02-17 18:29:45 [NOTICE] [configure] 1700 out of 2329 done.
2021-02-17 18:30:43 [NOTICE] [configure] 1800 out of 2329 done.
2021-02-17 18:30:43 [NOTICE] [configure] 1900 out of 2329 done.
2021-02-17 18:30:43 [NOTICE] [configure] 2000 out of 2329 done.
2021-02-17 18:30:43 [NOTICE] [configure] 2100 out of 2329 done.
2021-02-17 18:30:44 [NOTICE] [configure] 2200 out of 2329 done.
2021-02-17 18:30:57 [NOTICE] [configure] 2300 out of 2329 done.
2021-02-17 18:31:03 [NOTICE] [configure] System configuration has finished.
2021-02-17 18:31:03 [NOTICE] [post] Executing hooks in group post

Actions #1

Updated by William Clark about 3 years ago

  • Subject changed from The Configure section for new satellite-installer output should show progress bar or single line update about completed vs total tasks to Change configuration steps log message frequency and wording
Actions #2

Updated by The Foreman Bot about 3 years ago

  • Status changed from New to Ready For Testing
  • Assignee set to William Clark
  • Pull request https://github.com/theforeman/kafo/pull/324 added
Actions #3

Updated by The Foreman Bot about 3 years ago

  • Pull request https://github.com/theforeman/kafo/pull/325 added
Actions #4

Updated by William Clark about 3 years ago

  • Status changed from Ready For Testing to Closed
Actions