Foreman 1.19 Schedule

Release manager: Tomer Brisker and Ewoud Kohl van Wijngaarden
To be timed for approximately three months after the 1.18.0 release (see Foreman_118_Schedule).

Dates are subject to change and may slip.

  1. 16 April: development start (1.18-stable branched)
  2. 17 June: 1 month branch warning to dev
  3. 16 July: branch to 1.19-stable
  4. approx every two weeks since then, new release candidate until stable (usually 2 or 3 needed)
  5. approx mid August: release 1.19.0