Foreman 1.22 Schedule

Release manager: Tomer Brisker and Ewoud Kohl van Wijngaarden
To be timed for approximately three months after the 1.21.0 release (see Foreman_121_Schedule).

Dates are subject to change and may slip.

  1. 14 January: development start (1.21-stable branched)
  2. 14 March: 1 month branch warning to developers
  3. 7 April: stabilization period
  4. 21 April: branch to 1.22-stable
  5. 29 April: 1.22.0-RC1
  6. 28 May: 1.22.0-RC2
  7. 5 June: 1.22.0 GA